Document km6qKOLkYQa6pbko064mjqpYV
SM-32 (REV. 5-78)
Shell Oil Company
Interoffice Memorandum
DECEMBER 19, 1988
PLAINTIFF'S EXHIBIT SI 1-2 973
FROM:
STAFF INDUSTRIAL HYGIENIST, PRODUCTS HEALTH & SAFETY, HEAD OFFICE
TO: ATTACHED DISTRIBUTION LIST
SUBJECT: AGGREGATE RESULTS OF INITIAL ASBESTOS MONITORING
Attached for your consideration is a summarization of the results of the initial 30-minute asbestos monitoring which was submitted to this office in November and/or December. It is suggested that this data be used for priority setting and planning purposes only. Very few measure ments were found to approach or exceed the 1.0 f/cc limit. Based on available data, the potential for exceeding this limit appears to be' associated with tasks designated as "insulation removal."
P. J. Snydlr
PJS.-PJW
Attachment
cc: J. P. Chadwick C. F. Phillips J. L. Rivard
BJU8835403
ABS-060728 LAM 031304
DISTRIBUTION LIST
MANUFACTURING LOCATIONS
Anacortes -F. J. King
Belpre
-M. W. Hershman
Deer Park -W. B. Austin
Geismar
-T. L. Rodeheaver
Martinez
-M. B. Leeds
Norco
-A. K. Menard
Odessa
-R. D. Quisenberry
Taft
-A. J. Gauthreaux
Wilmington -S. V. Sever
Wood River -W. M. Cunningham
PRODUCTS DISTRIBUTION LOCATIONS
Metairie - A. J. Landry
Sewaren
- D. E. Eitel
Will bridge - C. F. Goetze
WESTHOLLOW RESEARCH CENTER W. F. Nail
HEAD OFFICE 0. D. Long J. D. Ransdell
UNDER SEPARATE COVER LETTER Shell Pipe Line Corporation - M. G. Kohnke
BJU8835403
ABS-060729 LAM 031305
RESULTS OF INITIAL 30 MINUTE ASBESTOS MONITORING SUMMARIZED BY TASK DECEMBER 1988
GASKET REMOVAL
RESULTS F/CC [28-32 min. S>: Time!
Geismar 1. 10 min removal -from sight-glass
<.01
2. Removed Durabla gasket from 3" pipe using flat metal scraper. Took 8 minutes to complete.
.01
3. Removed a Durabla gasket from a pump using flat metal^scraper. Took 16 minutes to complete.
<.01
4. Removed 4 gaskets from header using flat metal scraper. Took 12 minutes to complete.
<.01
Martinez 5. Cleaning gasket surface with wire wheel; no ctrls
.054
GASKET CUTTING
Geismar 1. Cut a pump gasket from Durabla gasket type
material. 3 minutes required to complete.
2. Cut two gaskets from Durabla gasket material using hand shears. Took 20 minutes to complete.
Norco 3. Worse case mock up: Welder cutting Durabla Gasket
for entire 30 minute period using gasket cutting machine in East Site Central Maintenance shop.
Wood River 4. Cutting Durabla Gaskets in Tin Shop. Cutter was
equipped with local hepa filtered ventilation.
.01 .01 .124
.19
PICKING UP. SWEEPING AND VACUUMING UP A PAD
Deer Park 1. Contractor performing general clean up work in
A unit.
<.01
BAGGING WET ASBESTOS CONTAINING INSULATION
Norco 1. Contractor bagging insulation inside roped off
area at Cat Cracker. Other workers nearby performing similar work.
<.033
ABS-060730 LAM 031306
BAGGING WET ASBESTOS CONTAINING INSULATION CONTINUED Deer Park 2. Picked up insulation and bagged it (A Unit)
5. 16 minutes. Bagged and double bagged asbestos in pipe rack; cleaned up area when finished and emptied hepa vac
4. Collected and placed asbestos insulation into plastic bag; 39 minute sample.
5. Placed asbestos insulation into bag and then double bagged.
6. Placed asbestos insulation into bags and then double bagged in BA/SR area
7. Placed asbestos insulation in bags and then double bagged in BA/SR area
<.01 <.10
<.10 <.10 <.10 <.10
PG. 2
HANDLING CLOSED BAGS OF ASBESTOS CONTAINING INSULATION
Wood River 1. Picked up 4 bags wet -from rain; carried bags
about 8 ft to closed top asbestos dumpster.
.01
COLLECTION OF BULK SAMPLES OF DUST AND DEBRIS FOR ANALYSIS
Wood River 1. Gathered bulk samples of dust and debris for
analysis.
<.07
WORKING ON EQUIPMENT PREVIOUSLY STRIPPED OF ASBESTOS
Wood River 1. Replace 4 steam valves on line that had been
stipped; asbestos still in vicinity. 34 min sx.
2. Same as #1 30 minute sx
3. Same as #1 35 minute sx
4. Same as #1 18 minute sx
REMOVAL ASBESTOS CONTAINING INSULATION
Norco 1. One of three contractors removing
at elevated platform inside roped Cracker.
wet off
insulation area at Cat
<.06 <.05 <.05 <.09
<.034
ABS-060731 lam 031307
REMOVAL ASBESTOS CONTAINING INSULATION CONTINUED
Wood River
2. Removed 1/2 " packing (dry) material from sides
of 2 tube bundles. Appeared to be non-friable.
No scraping or brushing.
13 minute sample.
3. Removed insulation from tee above exchangers using wet method. Some overhead work involved thus creating a possibility for falling debris, although none was reported.
4. Working with #3 above.
5. Removed insulation from large elbow on turbine using wet method.
6. Same as #5
7. Removed insulation by Reactor using wet method.
8. Same as #7
Shell Western E&P Kernridge 9. Removing insulation from hose bib and hydrant
Deer Park 10. Removed asbestos insulation off pipe in pipe
rack in "A Unit" using wet method.
11. Cut and removed insulation from pipe in pipe rack 39 minute sample.
12. Cut and removed insulation off flat sections of furnace
13. Pulled asbestos insulation off furnace tubes at "u" turns on end of furnace; 27 minute sample
14. Wetted down and chipped insulation off steel beams and expansion joints with pneumatic chisel between two columns.
Wi1 mington 15. Removing insulation from 2" pipe,
using wet method
140 ft long
Martinez 16. Insulation
blow still wet method
stripping (bulk pipe cover) from suction line in Asphalt plant using and encapsulating agent
.18
.29
1.13 .05
.54 <.01 . 13
.16 .49 <.10 <.10 <.10
<.10
.80
<.003
PG
ABS-060732 LAM 031308
o
CN
REMOVAL ASBESTOS CONTAINING INSULATION CONTINUED
17. Same as #16; insulation is < 257. asbestos
18. Same as #16
Metairie Plant 19. Removal and bagging of block pipe cover on
piping using water and an encapsulating agent; asbestos content greater than 257.. Work done in Grease plant mezzanine
Same as #19 (in pump house)
21. Same as #19.
22. Same as #20.
23. Same as #20.
24. Same as #20.
Wil lbridge 25. Outdoor removal of insulation usi ng glove bag
26. Outdoor removal of insulation using g 1 ove bag
27. Outdoor removal of insulation using glove bag
28. Outdoor removal of insulation using glove bag
29. Outdoor removal of insulation using glove bag
.01 .04
.06
F'G. 4
.09 .29 1.07 .23 . 05
.022 . 0097 .09 .016 < .01
DRILLING HOLES IN INSULATION
Martinez 1. Insulator drilled holes in block pipe cover using
wet method in Lubricants unit
<.06
2. Same as #1
<.06
2. Same as #1
<.06
REMOVAL OF JAR WRAP CONTAINING ASBESTOS
Deer Park 1. Chipped off and bagged tar wrap off old pipeline
in dock area; 24 minute sample
2. Same as #1
<.10 <. 10
ABS-060733 LAM 031309
BRAKE REPAIR
Wood River 1. Disc Brake job on a pickup, -front end.
Used Nil-fisk Wheel enclosure. 34 min sx.
.02
BRAKE REPAIR CONTINUED Swepi-Kernridge 2. Replacing brakeshoes
sample.
onpumping unit.20 minute
<.01
Wilmington 3. Drum brake 4. Same as #3 5. Same as #3
job on vehicle using wet method
.06 .03 .03
BRAKE CHECK
Martinez 1. Performing brake check on vehicle inside garage
.01
REMOVAL INSIDE ENCLOSURES
Norco 1. Contractor removing wet asbestos containing
insulation inside cocooned enclosure with 2 other workers. Insulation had been sprayed with water immediately prior to monitoring.
.356
2. Second contractor worker removing insulation in cocooned enclosure described in #2; Was working with very friable insulation material that had not been sufficiently wetted prior to its removal.
2.166
VACUUMING CONTAMINATED CLOTHING Norco 1. Contractor worker inside decontamination trailer
vacuuming disposable coveralls for 10 minutes. No other employees present. Remainder of time spent inside the trailer. Portable hepa vac used.
<.033
Deer Park 2. 5 minute sample. Vacuumed clothing and
and removed coveralls, washed hard hat, and respirator.
boots goggles,
3. 5 minute sample. Same as #2
<.10 <.10
PG. 5
ABS-060734 LAM 031310
EMPTYING HEPA VACUUM CLEANER
Deer Park
1. Opened hepa vac and changed out -filter bag and
<.10
cleaned and reassembled for use. 18 minute sample.
2. Same as #1
<.10
SEALING OF EXPOSED INSULATION OUTDOORS
Martinez 1. Sealing of exposed insulation on Column in
Furfural unit
2. Same as #1; asbestos content > 257.
.27 .02
PG.6
ABS-060735 LAM 0313H
December 19, 1988
Shell Oil Company
One Shell Plaza P.O. Box 2463 Houston, Texas 77252
She'll Pipe Line Corporation Mr. M. G. Kohnke
Dear Morris:
Pursuant to the service agreement between Shell Oil Company and Shell Pipe Line Corporation, the attached memorandum dated December 19, 1988, regarding "Aggregate Results of Initial Asbestos Monitoring" is for your information.
Sincerely,
P. J. Snyder Staff Industrial Hygienist Products Health & Safety
PJS:PJW
Attachment
BJU8835403
ABS-060736 LAM 031312